1. What is Complying Development?
Complying Development is a fast-track approval pathway in NSW.
Instead of going through a full Development Application (DA) with council, certain types of straightforward, low-impact development can be approved by a Private Certifier or Council under the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 (Codes SEPP).
- It combines planning approval and construction approval into one process.
- If the design fully complies with the standards in the Codes SEPP, the certifier must issue a Complying Development Certificate (CDC).
- Timeframe: typically 10–20 days, compared to several months for a DA.
2. Why is CDC Important for Project Managers?
As a Project Manager (PM) in an architectural practice, understanding CDC helps you:
- Assess feasibility quickly: some projects can bypass council DA.
- Save time and costs for the client.
- Decide the right approval pathway: DA vs CDC.
- Avoid design rework: CDC has strict standards — if not met, the design must go back to DA.
3. What Types of Development Qualify?
CDC applies to common residential and commercial projects, such as:
- New single and two-storey houses.
- Alterations and additions to houses.
- Secondary dwellings (granny flats).
- Garages, carports, fences, pools.
- Certain industrial and commercial developments.
Each development type has its own set of standards in the Codes SEPP.
4. Key Criteria for CDC Approval
For a project to be approved as Complying Development, it must satisfy:
- Zoning Permissibility
- The land must allow the proposed use under the LEP.
- Lot Standards
- Minimum lot size, width, and frontage requirements.
- Setbacks & Building Envelopes
- Strict distance rules from boundaries, roads, and other structures.
- Building Height & Floor Area
- Maximum heights and gross floor area limits.
- Environmental Constraints
- CDC is not allowed if the site has certain restrictions, such as:
- Flood control lot
- Bushfire prone land (without additional compliance)
- Heritage item or conservation area
- Critical habitat or environmentally sensitive land
- CDC is not allowed if the site has certain restrictions, such as:
- Utility & Infrastructure Requirements
- Adequate stormwater drainage, parking, and access must be demonstrated.
5. The CDC Process: Step by Step
- Site Feasibility Check
- PM reviews the LEP + Codes SEPP to confirm site eligibility.
- Exclude projects on heritage or environmentally constrained land.
- Design to CDC Standards
- Work with the architect to design strictly within the Codes SEPP rules.
- No flexibility — 100% compliance is required.
- Consult with Certifier
- Engage a Private Certifier early to confirm interpretation of rules.
- Prepare Documentation
- Architectural plans
- BASIX Certificate (if residential)
- Structural engineering drawings (if required)
- Stormwater & drainage plans
- Survey plan
- Lodge Application
- Submit to Private Certifier or Council for assessment.
- CDC Issued
- Approval covers both planning and construction.
- Construction can commence once the certifier is satisfied with documentation.
6. Key Differences: DA vs CDC
| Feature | Development Application (DA) | Complying Development (CDC) |
|---|---|---|
| Assessment body | Council | Private Certifier or Council |
| Timeframe | Months (often 3–12) | ~10–20 days |
| Flexibility | Can vary rules with justification | Must meet all rules exactly |
| Use | Complex or sensitive projects | Simple, low-impact projects |
| Public Notification | Yes (neighbours can object) | No |
7. Project Manager’s Role in CDC Projects
As a PM, your responsibilities include:
- Early Assessment: Determine if the project is suitable for CDC.
- Managing Expectations: Explain to clients the strict “all-or-nothing” compliance.
- Certifier Coordination: Engage and liaise with a certifier early.
- Documentation Oversight: Ensure all reports and plans align with Codes SEPP.
- Risk Management: If one rule cannot be met, shift strategy to DA early to avoid delays.
8. Key Takeaways
- CDC is faster and simpler than a DA, but only for compliant projects.
- Strict compliance is mandatory — no room for negotiation.
- PMs should always check eligibility early, before design progresses too far.
- The certifier is your main approval authority, not the council.
- If CDC isn’t possible, prepare for a DA pathway instead.